It has been a challeging 1st year for the Persatuan Penduduk JPP2

new-year-2013-psd

 

 the chronicle review of  TPP8A  till 31/12/2012

  1. 11/04/2011, We had 100% of the 197 unit owners agreed and signed for the application for the erection of perimeter fencing and guard house to the Yang Dipertua Majlis Perbandaran Sepang.
  2. 24/9/2011, the second meeting of the protem resident association of phase 8A initiated by the developer was held at the conference room of Plenitude Permai office, the agenda of the meeting were election of the committee and office bearer and appointment of security company for phase 8A to succeed the soon expiring  prepaid 6 month security service . however the meeting were attended by some 26 unit owners only (13%), following that the protem committee decided to have a total reach out and a massive exercise to launch a campaign of referendum on setting up a Gated and Guarded Community Scheme.
  3. 15/11/2011, Over 80% of the unit owner responded positive or supportive and returned with the signed referendum to endorse the RA for managing the security booth and hiring of KDN licensed security firm and approved the collection of setup cost and maintenance / security fees. ( 1–2% disagreed with the rate/concept, and about 10% not responded to our referendum but did signed for the application for the erection of guard-house and fencing)
  4. Gradually, nearly 95% of the units had been contributing to the setup cost and the  fourth monthly maintenance/ security fees to date.
  5. 15/12/2011. The RA took over the hiring/control of PP8A security service from the developer after the expiry of 6 months prepaid (6xRM80.00/month) mandatory maintenance plan imposed to every unit purchaser during the key handing over of the purchased unit.
  6. 14/12/2011 Successfully requested RM2.6 million allocation from Selangor state government through Senior Exco YB Teresa Kok to re-build the sinkhole road (Jalan Putra Prima Utara) after closing for nearly 3 years.
  7. 4th Jan 2012. The Persatuan Penduduk JPP2 was officially formed and registered with the Registrar of Society.
  8. Within couple of months nearly all the facilities mentioned / promised in the referendum had been gradually installed, commissioned and functioning properly, including but not limited to electricity, water, telephone, broadband utility connection, 3 motorised boom gates equiped with Touch & Go card reader access.  8 infra-red cameras CCTV 24 hour recording and with distant /remote monitoring capability via smart phone and computer internet. Spot lighting, road signed board, collapsible road divider with night vision enhanced reflector, 2 electric oscillating fan , 1HP split unit air condition unit, adjustable venetian blind sun-breaker. Acer desk top computer  was purchased to administer, monitor and record the card access system and a Acer laptop  plus laser printer to update and to manage the collection status.
  9. 13/6/2012 Obtained guard-house building plan approval from MPSepang
  10. 30/6/2012, Successfully organised ground breaking grand ceremony and invited many VVIP including Senior Exco YB Teresa Kok, MP Puchong YB Gobind Singh, YDP MPSeapang, Tuan Sayuthi, 7 Ahli Majlis including Mr. Santokh Singh, Mr. Lwi Kian Keong, Pengarah Kejuruteraan En Zulkefli Bin Mohd Arif, and several Top managers from Plenitude Bhd and some 500 residents attended the function accompanied and graced by 2 lion dance troupes. Food catering sponsored by developer Plenitude Permai Sdn bhd.
  11. By 31/12/2012 – Successfully put up and maintain this informative Blog with total 58 posts, 7 categories spreading over 21 pages, with over 240 comments or respondents and visited by some 17,780 viewers all times.
  12. By 31/12/2012 No incident of car been stolen, robbery, assults or fighting causing bodily injury  was reported within the compound of the gated and guarded community over the entire year of 2012 and before.

Last year  (2012) was indeed a very difficult year for the inexperienced and green RA to bring about all these  security setup to TPP8A and to materialize all those agenda listed above, where the RA was virtually given no guidance and assistance at all from the developer, we painfully worked through the dark or predicament and managed to overcome most of the obstacles, shortcomings, and even some sabotage acts from certain groups.

We hope the year 2013 will be a better and smoother one, Once again the RA would like to take this opportunity to thank all the residents for your past, present and future continuing support . And lets us worked together to upkeep all these facilities and installation,  look after the cleanliness of your neighbourhood  or surroundings and abide to the house rules and regulation to make our Taman the best buy for your property investment, the envy by others  and a better place to live and to raise your children/family.

Happy New Year to all the residents of Taman Putra Prima 8A and best wishes from:

Persatuan Penduduk JPP2

Kong Kok Meng (Chairman)

For any reason if you are not happy with your garbage collection

imagesCAWM3BLF

Please call direct number below

KONTRAKTOR KUTIPAN SAMPAH DI KAWASAN MPSEPANG

(1 MAC 2012 – 28 FEBRUARI 2015)

 

BIL
NAMA KONTRAKTOR
LOKASI KERJA
1
LAYANG LAGENDA ENTERPRISE
03-8768 0177
012-3067177
En Azuan
012 356 6177
016 238 2974
KERJA-KERJA KUTIPAN SAMPAH DISELURUH KAWASAN PERUMAHAN KOMERSIAL KILANG TONG BERPUSAT DAN KAWASAN BERKAITAN DI ZON SA 1(TAMAN MAS, TAMAN PUTRA PRIMA, TAMAN PUTRA IMPIANA,TAMAN MERANTI PERMAI INDUSTRI, TAMAN MERANTI JAYA INDUSTRI, TAMAN MERANTI JAYA

 

Image

Collection notice for the next 4 months of security and maintenance fees

Sample cheque 2

A Very Kind Advice

For the good of all parties please refrain from paying cash to avoid any mishandling or recording error by the security guards. Kindly be adviced to open a current account in your bank for the ease of tracing transaction records.

As the Treasurer and your Zone leaders are all volunteers working for us by squeezing from their little left spare time after the tiring day work. So let’s make everyone happy and easy……..Appreciation from the RA

温馨劝告

以防保安人员的疏忽或不慎和为了大家的方便与安全,  请帮忙尽量避免付现金. 为了方便大家询查支票过账, 请开设一个银行来往账户

居协会财政和分区组长都是志愿者, 他们每天都为生活劳累的工作后还要挤抽出一点业余或和家人休息的时间为社区服务。因此让我们大家一致合作好让每个人(居民或居委)都过得更融洽, 更轻松, 更愉快,….谢谢.

Collection notice 4 months-page-001 (2)

Finally traffic lights were installed at Taman Putra Prima main entrance T-junction after long awaited joint petition from several resident associations

Traffic lights were installed

Traffic lights were installed

For more history, please read at earlier post published on 17th May 2012

Traffic Light-page-001

MPSepang Councillors will bring the sinkhole incident and slow progress of the RM2.6M sunken road repair works to OSC meeting tomorrow

Councillor Santokh Singh pointing at the bill board stating the completion  of work is  01/10/2012

Councillor Santokh Singh pointing at the bill board stating the completion of work is 01/10/2012

Councillor Santokh Singh, Councillor Pulanthran and RA Chairman Kong Kok Meng were inspecting the sinkhole right in front of PP8a main entrance

Councillor Santokh Singh, Councillor Pulanthran and RA Chairman Kong Kok Meng were inspecting the sinkhole right in front of PP8a main entrance

Tarikh Siap 01/10/2012

Tarikh Siap 01/10/2012

The sinkhole at PP8a main entrance is getting bigger and deeper now, post imminent danger to all residents.

Another big sinkhole happened right in front of PP8A main entrance

The RA chairman had notified the contractor, Consultant Engineer Ikram, and Pengarah Kejuruteraan MPSepang this morning,  Majlis technicians visited the scene immediately after receiving notification from the chairman.

 

 

The causing of Sinkhole
More commonly, sinkholes occur in urban areas due to water main breaks or sewer collapses when old pipes give way. They can also occur from the overpumping and extraction of groundwater and subsurface fluids. They can also form when natural water-drainage patterns are changed and new water-diversion systems are developed. Some sinkholes form when the land surface is changed, such as when industrial and runoff-storage ponds are created; the substantial weight of the new material can trigger an underground collapse of supporting material, thus, causing a sinkhole.

Sinkholes can be triggered by human activities such as:

  • Overwithdrawal of groundwater
  • Diverting surface water from a large area and concentrating it in a single point
  • Artificially creating ponds of surface water 
  • Drilling new water wells

Typical activities that can lead to sinkholes are:

  • Decline of water levels – drought, groundwater pumping (wells, quarries, mines)
  • Disturbance of the soil – digging through soil layers, soil removal, drilling
  • Point-source of water – leaking water/sewer pipes, injection of water
  • Concentration of water flow – stormwater drains, swales, etc.
  • Water impoundments – basins, ponds, dams
  • Heavy loads on the surface – structures, equipment
  • Vibration – traffic, blasting

From several sources of literature and facts finding, it is evidently that our stretch of road (Jalan Putra Prima Utara) facing the water retention basin (artificial pond) was more vulnerable to the occurrence of sinkhole especially after the year-end monsoon rainy season.

Sources:

http://www.sjrwmd.com/watersupply/howsinkholesform.html

http://www.portal.state.pa.us/portal/server.pt/community/sinkholes/10637/what_causes_a_sinkhole_/554362

Actual scene at Jalan Putra Prima Utara before the RM2.6M repair works

Hopefully this will not happen right at PP8A entrance

Picture from elswhere

PP8a native waterhen roaming / foraging near the wetland lotus pond

 

See video Link below

Video and pictures were taken by Chairman on 26/11/2012 with 42X zoom len Nikon camera from over 50m distant balcony.

http://www.youtube.com/watch?v=-hGyRO-lx_w

 

Would you like to see PP8A fencing to be in this state after months or perhaps a year from now?

These pictures were taken from Taman Putra Prima various phases . (Note: all pictures with date inprint)

Those phases were handed over to purchasers  just about one or two years earlier than our phase 8A.

This slideshow requires JavaScript.

the grass is over grown, the fence can hardly carry the loading

T

the chairman hire worker at his own cost to clear the over grown weed exerting load on the weak fencing to prevent it from falling.

 

The clear path was maintained by the Chairman with his own worker/machine at his own cost for nearly a year before the Majlis took over after much solicitation.

How long will these well trimmed grasses / lawn and neat fencing at 8A going to stay, if the RA is not fully backed or echoed by the residents………

Neatly trimmed grass to both sides of the well maintained fencing at PP8A

Grass outside the perimeter fencing of PP8A is well trimmed to ease off pressure onto the poor quality and weakly supported chain link fence

 

 

 

 

 

 

 

 

Could this below be the only long term solution to safe guard your security and property value and to maintain the successful  Gated and Guarded Community Scheme exclusive image?

A more durable, stronger and better looking Galvanized BRC fencing will certainly give added security and value to your home or investment

Example of Galvanized BRC Mesh fencing

New schools badly needed in Puchong 蒲种华小爆满

(The Star Monday November 12, 2012)

There are currently four Chinese primary schools in Puchong with a total of 12,000 pupils. Due to increased population, some 1,500 students have to study in schools outside Puchong.

(蒲种11月9日讯)蒲种区人口剧增,单是区内4所华小生即达1万2000人,仍有1500人被迫到区外接受母语教育。

Taman Putra Prima Primary School Reserved Land

tpp

http://thestar.com.my/metro/story.asp?sec=central&file=/2012/11/12/central/12300407

http://www.nanyang.com/node/490786?tid=510

http://goodtimes.my/index.php/Politics-Government/chinese-schools-in-demand-in-puchong.html

http://putraprimapuchong.blogspot.com/2012/03/land-clearing-in-taman-putra-prima.html

Shall we (Taman Putra Prima Residents) jointly petition for one SRJK (C) in Taman Putra Prima???